
|
 |
Law Talk - Premature Recordation of a Mechanic's Lien May Invalidate The
Lien
By Sam K. Abdulaziz
Attorney at Law
In a recent California Appellate Court case, the court
examined the issue of recording a mechanic’s lien before completion of the
contract. This case was decided by the lower court, then the losing party
appealed to the appellate court. The appellate court in Howard S. Wright
Construction Co. v. BBIC Investors, LLC disagreed with the lower court when it
reviewed whether Wright’s mechanic’s lien was recorded too early.
BBIC Investors, Inc. (OWNER), the owners of a former warehouse building, leased
out space to 360networks (USA) Inc. (LESSEE). As a telecommunications company,
LESSEE needed a high-tech facility for its Internet business. LESSEE hired
Howard S. Wright Construction Co. (CONTRACTOR) to do the work and entered into a
Design Build Agreement with them. Under this Agreement, CONTRACTOR would convert
a warehouse into a modern Internet facility. The total project budget was
approximately $5.2 million.
OWNER posted a notice of nonresponsibility. They did so in an effort to prevent
attachment of any mechanic’s lien to the property.
In March 2001, CONTRACTOR began work on the project. By May and with about 65%
of the project complete, it was clear that LESSEE was having financial problems.
LESSEE asked that the project be placed on hold. At that time, CONTRACTOR
arranged to do what was necessary to leave the site.
On May 24, CONTRACTOR sent LESSEE a letter with the subject line reading
“Authorization for Final Close-Out Work.” On May 29, LESSEE responded
authorizing CONTRACTOR to go ahead with the closeout work. This closeout work
would cost $194,950.00. Although final inspection was set for June 26, on June
18, LESSEE told CONTRACTOR that it did not intend to pay any more money. On June
19, CONTRACTOR sent a letter to LESSEE confirming their conversation and moved
its people off the site. The very next day, CONTRACTOR recorded a mechanic’s
lien.
A mechanic’s lien can be filed only after completion of the project. The code
has several definitions for “completion.” CONTRACTOR argued that work was
substantially completed on June 19, since that was the last day subcontractors
pulled material or did any work on the project. However, CONTRACTOR’s job diary
showed that on June 26, CONTRACTOR moved some ductwork and did the closeout
inspection. Therefore, OWNER said that the June 20th mechanic’s lien was
premature (recorded before completion of the project), thus invalid.
In court, CONTRACTOR made two arguments. First, they said there were really two
projects – one was the original construction of the site and the other was the
close-out work. CONTRACTOR argued that LESSEE abandoned the original
construction project in May, which constituted actual completion under Civil
Code section 3086. Second, as an alternative argument, CONTRACTOR argued their
lien was timely recorded because under Section 3086 a lien could be recorded 60
days after work stopped on June 19.
However, the lower court did not agree with CONTRACTOR. The lower court said
that the lien was recorded too early because according to Section 3115
completion occurs 60 days after cessation of work. In addition, the court found
that the project did not end until June 26 – the date they last did any work at
the site. Therefore, “completion” did not occur until sometime in late August,
which was long after the lien was recorded.
On appeal, the court felt the trial court interpreted the statutes wrong. The
majority of the appellate court’s opinion was an analysis of the meaning of the
phrase “completes his contract” in Section 3115. The court pointed out that a
contract can never be considered complete unless all the work was performed.
Therefore, as in this case, when a contract is cut short, a contractor could
never timely record its lien. This obviously goes against common sense.
Therefore, the court concluded that “a contract is complete for purposes of
commencing the recordation period…when all work under the contract has been
performed, excused, or otherwise discharged.”
First, the appellate court found that there was only one project, not two, as
CONTRACTOR tried to argue. Second, applying the above rule, LESSEE’s obligations
with CONTRACTOR ended on June 19. Remember, that was the day LESSEE
anticipatorily breached the contract. Anticipatory breach is a legal term
referring to a situation where a party to a contract makes clear that they are
not going to uphold their side of the bargain. If it is significant, the other
party’s obligations end and he is allowed to sue.
Finally, due to LESSEE’s anticipatory breach, the contract was complete on June
19. It follows that the lien was timely recorded.
This case is a clearly shows how two courts can reach two different conclusions
when interpreting the law. It is just another a reason why a contractor needs a
competent construction attorney when dealing with a legal dispute.
Return to Year 2007
Topics
The information and comments throughout this website are intended to be of a general nature. Our comments/advice should not be relied upon without your seeking the aid and advice of legal counsel who will have the opportunity to take the time to research all your issues.
Abdulaziz, Grossbart & Rudman provides this information as a service to its friends &
clients. It is of a general nature and should not be used as a substitute for
specific legal advice. Any and all information set forth on our website relates
solely to California law. The information is not relevant and not applicable in
any other state or jurisdiction.
The firm can be reached at:
Abdulaziz, Grossbart & Rudman
P.O. Box 15458
North Hollywood, CA 91615-5458
(818) 760-2000
Facsimile (818) 760-3908 or by E-Mail at
Info@AGRLaw.net
Please note that any information you provide to
us via e-mail may be viewed by others and therefore, it is not a privileged
communication.
Copyright © 2006 by Abdulaziz, Grossbart & Rudman. All rights reserved.
|
 |