
|
 |
Law Talk - When is a Project Complete?
By Sam K. Abdulaziz
Attorney at Law
This article deals with completion on a
construction project. However, it is not intended to be a complete analysis of
mechanic’s liens. For that, you need to seek the aid and advice of a competent
construction attorney.
Contractors are one of the only professions that are allowed to record a lien
against property, and tie up that property, securing their payment even before a
lawsuit is filed. The right to a mechanic’s lien is protected by the California
Constitution. However, the Legislature has tried to balance the rights of the
contractors against the rights of owners, and has set forth a number of
limitations on enforcement of lien rights. One of those limitations is that a
mechanic’s lien must be recorded within a short period of time after
“completion” of a project. If you are the “original contractor,” which means the
person under contract with the owner, you have 90 days from “completion” of the
project to record a mechanic’s lien, unless a Notice of Completion has been
recorded, at which point, the original contractor has 60 days. A subcontractor’s
lien rights are shortened from 90 days to 30 days by the recording of a Notice
of Completion. The Notice of Completion itself is required to be recorded within
ten days of completion. If it is not recorded within ten days of completion, the
statute provides that it is ineffective to shorten the lien period and then
everyone has 90 days.
The Legislature has passed a law that would require any one who records a Notice
of Completion or a Notice of Cessation of Labor, to send a notice to anyone who
gave that owner a Preliminary Notice. The Notice of Completion must be sent by
certified mail, within ten (10) days of recording the Notice of Completion.
The rule requiring notification of the recording of a notice of completion does
not apply to a person who occupies the real property as a personal residence so
long as the dwelling contains not more than four residential units. Thus, the
rule essentially does not apply to owner-occupied homes.
As to completion, Civil Code section 3086 defines completion to be “actual
completion of the work of improvement.” However, the statute also provides for
“equivalents” to completion: (a) the occupation or use of the work of
improvement by the owner, or his agent, accompanied by the cessation of labor;
(b) the acceptance by the owner, or his agent, of the work of improvement; (c) a
cessation of labor for a continuous period of 60 days (or thirty days if a
Notice of Cessation is recorded); or (d) if the work of improvement is subject
to acceptance by a public entity, the date of such acceptance.
Despite what appears to be a fairly clear definition, there have been a number
of cases on this subject. In one rather famous case, a contractor was working on
a project and there was four soap dispensers that were required to be installed
by the contract, which were on back order. The owner had contended that
completion occurred before the soap dishes were installed. The Court of Appeal
held that because there was work required under the contract that needed to be
performed, that the project was not complete. Accordingly, in that case, the
court held that the omission of the four soap dispensers that were part of the
contract meant that the project was not complete, and a mechanic’s lien that was
recorded later in time from the date that the owner declared it to be complete,
would be valid.
However, in other cases, the Court of Appeal has declared “trivial” or “punch
list” work does not extend the time for completion. This becomes a factual
question as to whether the work was merely to correct the work originally
performed, or to perform work that was required by the contract that was never
installed.
Return to Year 2007
Topics
The information and comments throughout this website are intended to be of a general nature. Our comments/advice should not be relied upon without your seeking the aid and advice of legal counsel who will have the opportunity to take the time to research all your issues.
Abdulaziz, Grossbart & Rudman provides this information as a service to its friends &
clients. It is of a general nature and should not be used as a substitute for
specific legal advice. Any and all information set forth on our website relates
solely to California law. The information is not relevant and not applicable in
any other state or jurisdiction.
The firm can be reached at:
Abdulaziz, Grossbart & Rudman
P.O. Box 15458
North Hollywood, CA 91615-5458
(818) 760-2000
Facsimile (818) 760-3908 or by E-Mail at
Info@AGRLaw.net
Please note that any information you provide to
us via e-mail may be viewed by others and therefore, it is not a privileged
communication.
Copyright © 2006 by Abdulaziz, Grossbart & Rudman. All rights reserved.
|
 |